This is a tentative timeline based upon the many variables that go along with the construction of a new buliding. The biggest variable at this time is the acquisition of funding. The final goal is to have the ribbon-cutting ceremony and open the doors to a debt-free building with the funds available to administer and operate the growing mission of the Catholic Student Center at Texas Tech University.
(Please note, this timeline is different from the one published in the Spring 2014 newsletter.)

  • July 2014 - meeting of user groups to discuss concept options
  • August 2014 - concept option review meeting
  • September 2014 - concept revisions based on feedback
  • October 2014 - approval of concepts
  • December 2014 - renderings of new facility
  • February 2015 - schematic design (preliminary)
  • March 2015 - design development
  • April 2015 - press conference announcing the project and the Raider Promise Capital Campaign
  • May 2015 - construction documents
  • June 2016 - bidding
  • July 2016 - construction administration
  • August 2017 - facility occupation